15 03, 2019

Television

2022-02-22T19:46:24+00:00

In-Progress  Starting D building Installs starting on PH level to G Level Upcoming The project will be fully complete by the end of February 2020. Completed B & C Building installs have been fully completed. Information updated: 2/06/2020

Television2022-02-22T19:46:24+00:00
15 03, 2019

Phone

2022-02-22T19:46:41+00:00

In-Progress Currently, there are no in-progress tasks while Hopper Installs are taking place. Upcoming Voicemail System Upgrade Completed Updated the fiber throughout every building to ensure a reliable and dedicated connection. Information updated: 2/6/2020

Phone2022-02-22T19:46:41+00:00
15 03, 2019

Internet

2022-02-22T19:46:48+00:00

In-Progress There are no in-progress tasks while Hopper Installs are taking place. Upcoming Faster, more reliable speeds through a service update - coming soon! Completed All internet access points completely installed in units.   Information updated: 2/6/2020

Internet2022-02-22T19:46:48+00:00