There are four stacks left to be painted in the D tower. We hope to have these done within the next 30 days . Tomorrow, September 20th, the paint crews will be moving to the B tower to begin the railings and window frame painting. We anticipate the completion of phase two paint project to be completed by April 2023 . The crew will be accessing all units through the entry door and will go directly to the balconies.The painting crews will begin at the penthouse level and make their way down. We appreciate your cooperation and we look forward to completing this job.
For any questions please reach out to your owner relations representative. Andrea Soars ([email protected]) B Tower, Jill Alford ([email protected]) C Tower, and Hayli Parnell ([email protected]) D Tower.